City of Buda seal

Bond Updates

Updates about the five propositions passed in the November 2014 election.

Dec 12

Bond Overview/Update - Props 1 - 5

Posted on December 12, 2017 at 8:27 AM by David Marino

It's been a while since we did an overall update on all of the bond propositions. We've included links below of the very latest. This update was presented at the Dec. 5, 2017 City Council meeting. 

Bond Update - Props 1- 4

City Park Update - Prop 5 (Parks and Trails)
Nov 07

Municipal Complex Update - Nov. 7, 2017

Posted on November 7, 2017 at 6:11 PM by David Marino

Hard to believe, but in a few weeks our police department will move into the new Public Safety building.

In April of this year, our crew poured the foundation for our the building. Fast forward 7 months and you have a completed structure.        

“They are currently in the process of moving in furniture. That will be finished towards the end of next week. We have a few minor items that we’re trying to finish up,” said Project Manager Ray Creswell. 

The police department is expected to start moving in around November 20th.

Over at the municipal building our crew is working hard.  

“On the first floor they are already doing the first coat of finishes on the walls. They are also beginning to lay in the ceiling grid. Throughout the lobby area they are currently putting in the new ceiling element. The framing is in place. On the second floor in the City Hall administrative area they are now closing in the walls on both sides. They are beginning to tape and bed the dry wall for finishes.”

The new library is also coming together.  

“In the library they are finalizing some of the framing. They are also beginning to close up both sides of the walls.”

In a matter of months, the Municipal Complex has taken shape and we are excited about the future.

“We are still on schedule for the end of April on the final finish out and turnover of the building.  

You can watch the video version of this story here: Municipal Complex Video Update - Nov. 7, 2017

Oct 19

Municipal Complex Update - Oct. 19, 2017

Posted on October 19, 2017 at 10:29 AM by David Marino

Another week brings more progress at the Municipal Site.  The inside of the City Hall and Library is taking shape.

“They’re going up with the dry wall on both sides. They have had inspections and have completed almost all of the in-wall and above ceiling,” said Project Manager Ray Creswell.  

City Council chambers have been walled in and the stone is now in place. The lobby area is also coming together.     

“The exterior portion or the lobby area, the finishes are now going up on the stone. A little bit of the metal that’s going in there will be going up pretty soon. We’re working on our way right on down into the library. You have your public toilet area, your classroom and then activity classrooms on either side that open up into the library. Those portions are beginning to have the walls completely closed in and the ceiling framing put in place.”

Work also continues on the drainage channel.

"They’re going up with the erosion mats on the side walls of the channel and are beginning to put in the landscape sub-grade and coming back in with the landscaping."    

The Public Safety building is almost finished.

“All exterior is complete. We do have some minor areas where they are beginning to touch up. Landscaping is taking place around the entire building. The parking lot has been completely paved and striped. The garage is approximately 90 percent complete."    

The Police department should be moving into the new building in mid-to-late November.

The City Hall and Library is expected to open in April of 2018.    

Below is a link to the video version of the story.   

Municipal Complex Update Video - Oct. 19, 2017