Sep 08

September 8, 2015 Update

Posted on September 8, 2015 at 2:50 PM by Melinda Hodges

Propositions 1, 2, and 5
On Monday, August 31st, Page held its first validation/programming meeting with the Steering Committee. The purpose of this meeting was to gather information from the committee members and begin the design of the Municipal Facility, Public Safety building, and Parks Maintenance building.
On Tuesday, September 1st. ECM and JE Dunn met with the project team to conduct a Value Proposition Canvas Workshop to develop and complete the project execution plan. This meeting focused on maximizing the efficiency of process, cost, and expedited schedule to deliver a successful project to the City of Buda.
Chaparral Surveying and Terracon have both been directed to begin the survey and geotechnical study of the Municipal Facility and the Public Safety building site within the next two weeks.
The program is on schedule to have design complete by July 1st, 2016 and construction complete by December 15th, 2017.

Propositions 3 and 4
Phase one design began in earnest the week of September 1st.

Proposition 5

ECM is currently in contract negotiations with Design Workshop for the design of the Parks and Trails projects. They anticipate presenting this contract to the City Council on September 15th, 2015.

Tag(s): Prop5, Prop4, Prop3, Prop2, Prop1