Old Goforth Update - August 1, 2019

Posted on August 1, 2019 at 4:26 PM by David Marino

Old Goforth Road Improvement Project

August 1, 2019 Update

The full right-of-way looking south from Stone Crest Boulevard. Curbs, gutters, inlets, and sidewalks are complete on the east side where the first course of pavement will go to permit one-way traffic. The east side is projected to open for one way traffic before August 15th! The projected completion of the project is mid-October!

3,350 square feet of engineered concrete block wall is being installed along the east side as a retaining wall. The retaining wall will have a level look the entire length - achieved by stepping up the footers at the appropriate locations to minimize cost and provide a long-term solution to meet the needs of our citizens!

The construction masonry crew began hand laying every block only five days ago....each block weighs approximately 60 lbs!

Old Goforth Road earthwork and retaining wall continues to near completion in preparation for paving to begin! Temporary paved one-way traffic will open in time for the start of school on August 15th!