Old Goforth Construction Update - Sept. 13, 2019

Posted on September 13, 2019 at 10:57 AM by David Marino

Old Goforth Construction Update: Old Goforth Road’s transition to being a “New” Goforth Road continues to take shape! Over the past week the work crews of the City’s contractor, Smith Construction, completed the nearly 4,000 square foot retaining wall, finished covering the full length the road’s east side with erosion control blanket, and 2,000 linear feet of curbing, gutter, and sidewalks along the west side. We thank the community for their observation of the signage and awareness of the work crews bringing this project closer to reality and completion. Currently, we anticipate the full road to open at the end of October...almost two months ahead of schedule. Old Goforth - Sept. 13, 2019 Old Goforth 2 - Sept. 13, 2019 Old Goforth 3 - Sept. 13, 2019