Main Street Improvement Project Update - Aug. 4, 2020

Posted on August 4, 2020 at 5:54 PM by David Marino

Main Street Improvement Project Update
Aug. 4, 2020

  • Phase I (southern half of Main Street) is complete!
    • The efforts of Cox Commercial Construction over the past several weeks resulted in the completion of Phase I ( the southern half of Main Street from Railroad to the divide on the east end.)
    • The major activities completed include:
      • Milling and partial excavation of the full length
      • New curb and gutters
      • Drainage improvements
      • New water and wastewater lines
      • New sidewalks and pedestrian lighting
  • Phase II (northern half of Main Street) begins this Thursday, Aug. 6, 2020 and will last approximately 110 days.
    • The traffic pattern will shift to two-way traffic on the south side this Wednesday, Aug. 5 and will include road surface painting and marking for traffic control
    • Traffic signal lights will change to align to the traffic lanes
    • Erosion control measures will be completed by this weekend
    • Milling of the northern half will begin on Monday, Aug. 10
    • Excavation for the new 24” effluent force main will begin on Tuesday, Aug. 11
  • Phase III of the project (full-width 2” surface overlay from Ash Street to the O’Reilly’s Auto Parts driveway) is expected to begin shortly after the Thanksgiving holiday.