  • The City Council approved execution of a professional services agreement (PSA) supplement for RPS Klotz to prepare final design plans, specifications, and an estimate (PS&E) for the Main Street Improvements Project - Segments 1 and 2.
  • The City Council authorized City staff and our Prop 3/4 Program Management consultant (HDR) to enter negotiations with RPS Klotz to develop a scope of work and fee proposal for PS&E for a future Cabela’s Drive connector road (Segment 4) and West Goforth Road improvements (Segment 5). Future execution of a PSA supplement with RPS Klotz is dependent upon remaining available Prop 3 funds after accounting for all prior commitments for project design and construction. 
  • The City Council agreed with the proposed discrete bid letting of Old Goforth Road with a Summer 2017 construction start.
  • The City Council did not take a final position on bundling the San Antonio Street, the RM 967 @ Main Street intersection, and the Main Street improvement projects.