Municipal Complex Drainage Work Update

Posted on November 14, 2016 at 3:50 PM by David Marino

Work at the Municipal Site continues. Our Public Works crew is finished back filling the concrete box culverts. The culverts arrived at the Municipal Site in September. Since then, crews have been working to get this part of the project done. The natural drainage on the property is being widened and deepened. It will be left as an improved natural channel on one end that transitions into a constructed drainage segment using the box culverts. 

Image of the box culverts