Bond Updates

Updates about the five propositions passed in the November 2014 election.

View All Posts

Jul 30

July 2015 Updates

Posted on July 30, 2015 at 11:42 AM by Melinda Hodges

We're making progress on all the bond projects! Here's where we are:

Propositions 1 and 2: Municipal Facility and Public Safety Office
The City publicized an RFQ for Architecture and Engineering Services to receive qualifications from interested firms. Thirteen firms responded with proposals. After the proposals were reviewed and scored, the top three firms were selected and interviewed. After the interviews, the Steering Committee selected ProForma Architecture. ECM is currently in contract negotiations with them.

The City publicized an RFP for Construction Manager at Risk. Four firms responded and all four were interviewed. JE Dunn has been selected as the Construction Manager at Risk Contractor. ECM has begun contract negotiations with them.

Propositions 3 and 4: Streets and Drainage
Ten firms responded to the City's RFQs for Streets and Drainage. For each RFQ, the three firms with the highest scores were interviewed. The firm chosen to perform design for the Streets project is RPS Klotz Associates. The firm chosen for the design of the drainage projects is Freese and Nichols. HDR is currently involved in contract negotiations with both firms.

Proposition 5: Parks & Trails
The City publicized an RFQ for design services for the Parks & Trails projects. Seven firms submitted responses; these responses are currently being reivewed by the Steering Committee and ECM.

Professional Services
At the July 21st meeting, ECM proposed the Steering Committee's recommendations for Professional Services, including Geotechnical Investigation, Surveying, Construction Materials Testing, Technical Inspection, Environmental Site Assessment, and Commissioning.

See more information and procurement schedules