Apr 13

April 2016 Updates

Posted to Bond Updates on April 13, 2016 at 10:50 AM by Melinda Hodges

Propositions 1 and 2
Schematic design for the City Hall/Library and Public Safety buildings is well underway. It is anticipated that the design will be presented to City Council for approval in April or May.

Proposition 3
On February 29th, 2016, Allen Crozier with HDR gave a presentation regarding the streets projects. This presentation was also given to the Buda Bond Advisory Committee at their March 24th, 2016 meeting. Both groups agreed on the following feedback:
  • Trees will not be removed along Main Street. City Council gave additional instructions for the engineers to think outside the box on ways to improve traffic on Main Street.
  • Continue with the planned improvements to Main Street at FM 967.
  • Continue with the planned improvements to Old Goforth Rd.
  • Of the four proposals for improvements to San Antonio Rd., both groups preferred option 4.

View the presentation here.

Proposition 4
The City has received the draft Preliminary Engineering Report from Freese and Nichols, regarding our drainage bond projects. This report is not final and has not been approved by City Council.
View the draft report here. (This is a very large file and may take some time to download.)

Proposition 5
The City of Buda has purchased a piece of land along Garison Road, just past the wastewater treatment plant, with the intent of creating a new park. Both the Parks Commission and the Prop 5 committee expressed the opinion that further Prop 5 funds should not be spent on this project. They would like to see a plan created for the park before any development is started. The City Council agreed with this plan of action.

Tag(s): Prop5, Prop4, Prop3, Prop2, Prop1

Sep 17

Seeing green ribbons around town?

Posted to Bond Updates on September 17, 2015 at 5:25 PM by Melinda Hodges

Have you see some green ribbons on poles and trees along Main Street, San Antonio Street, and on the new Municipal Facility/Public Safety site? These ribbons will help surveyors make a 3D map of these areas, which is needed for many of our bond projects. So when you see those green ribbons around town, they just mean we're making progress!

Tag(s): Prop4, Prop3, Prop2, Prop1

Sep 08

September 8, 2015 Update

Posted to Bond Updates on September 8, 2015 at 2:50 PM by Melinda Hodges

Propositions 1, 2, and 5
On Monday, August 31st, Page held its first validation/programming meeting with the Steering Committee. The purpose of this meeting was to gather information from the committee members and begin the design of the Municipal Facility, Public Safety building, and Parks Maintenance building.
On Tuesday, September 1st. ECM and JE Dunn met with the project team to conduct a Value Proposition Canvas Workshop to develop and complete the project execution plan. This meeting focused on maximizing the efficiency of process, cost, and expedited schedule to deliver a successful project to the City of Buda.
Chaparral Surveying and Terracon have both been directed to begin the survey and geotechnical study of the Municipal Facility and the Public Safety building site within the next two weeks.
The program is on schedule to have design complete by July 1st, 2016 and construction complete by December 15th, 2017.

Propositions 3 and 4
Phase one design began in earnest the week of September 1st.

Proposition 5

ECM is currently in contract negotiations with Design Workshop for the design of the Parks and Trails projects. They anticipate presenting this contract to the City Council on September 15th, 2015.