Bond Project Updates - Main Street (Between Cabelas and Railroad) and City Park

City Park - March 6, 2020

Bond Project Updates
Main Street & City Park
March 6, 2020
By Project Manager Kenny Crawford

We’ve all been there – passing that construction project that seems to be idle. Why does the construction schedule keep changing? This is a valid question and concern. First of all, we want to thank you for your continued patience as we finish up our bond-related projects.

During the design review, bid process, and execution of a construction project, a request to clarify a detail in the plans and specifications, unforeseen conflict, or to the scope will generate RFIs (Requests For Information). Sometimes, these RFIs generate triple constraints to project execution: a change to the scope of work, change to resourcing requirements (time, cost, labor), and a change to the project schedule - one is not affected without the other two being equally changed in some way – these are compiled into a single document called Change Orders.

One such example of a change order is unforeseen conflicts. These can be unmapped subsurface utilities or unknown subsurface conditions that may cause significant delays to a project schedule because there are no field solutions or “workarounds” suitable or acceptable as long-term solutions. Often, the discovery of subsurface infrastructure and unsuitable conditions generate requirements to further “explore” to determine the extent of the conditions to develop engineering redesign solutions that meet construction code and long-term suitability. This takes time. Sometimes, these discoveries are the ownership of other entities (i.e. communications, energy, abandoned infrastructure) whose schedule and resources are outside the influence of the City. These entities must be notified, they must schedule surveys and possibly generate alternative design solutions, schedule work, and execute the work to adjust to the overarching needs for improvements, growth, and development in City infrastructure projects. These are exactly some of the issues that have come into play with the Main Street Improvement Project between Cabelas and Railroad and the City Park Improvement Project. While unfortunate, it is these external influencers that may delay projects and significantly impact scope, schedule, and cost. It is also the discovery learning that subsequently drives change to move forward and continue progress.

Main Street Improvement Project Between Cabelas and Railroad

The Main Street Improvements Project, started on July 29, 2019 recently had a 60-day delay directly due to unforeseen conflicts with two external influencing entities. The result of the project is a 20-year life cycle grand-entryway into the heart of Buda. To provide perspective, the delay is 0.7% of the total lifecycle of the road. Doing this project right the first time is a necessary inconvenience in the overall scope. Cox Commercial Construction worked diligently along the entire length of the project area until they couldn’t work around multiple unforeseen conflicts any further and work stopped. Although a delay is unpleasant for everyone, there are a few good things that stemmed from this delay that will, likely, benefit the City and result in greater overarching efficiencies in project costs and long-term goals.

While not adding to the delay of the project any further, we are conducting a redesign of the new 24” effluent force main that will enable future connection to the expansion of the wastewater treatment plant when complete in August 2021. Cox Commercial Construction continued working on Main Street the week following the rerouting of the external influencer’s utilities and are going full steam ahead in preparing and building the south side of the road.

We learn from our experiences. The conflicts on the south side of Main Street helped us identify potential conflicts and design solutions that will mitigate future triple constraints in the second phase (north side) of Main Street. The City is working closely with the design engineer firm, RPS Klotz, and will self-perform subsurface utility and infrastructure assessment and inventory over the next thirty days at a significant cost savings to our taxpayers. While “hope is not a method,” this proactive approach will enable us to validate, design and adjust prior to construction beginning on the north side of Main Street. The new baseline completion for this project is expected to be the end of September 2020.

Meanwhile, Main Street in Downtown Buda is open. The project is moving along and there are some remaining elements that will be finished in the coming weeks.   

City Park Improvement Project

The City Park project began on April 29, 2019 with a massive earth moving effort by our City Public Works team, The Design Workshop and The Barr Company, AIA. As project efforts resumed through the summer, fall, and winter of 2019, over 100 RFIs resulted in 20 different change orders. The City requested 35% of the change orders for the betterment of the project and added value, the remaining 65% were due to design and field conditions. The City Council and City Manager approved and leveraged the use of the project contingency budget for approximately $210,000 to address the requirements and added 55 days to the duration of the project to execute the requisite changes to the project. The result of the project is a city park that will transcend generations right in the heart of Buda. Doing this project right the first time is a necessary inconvenience in the overall scope. The new baseline completion for the City Park is expected to be the end of June 2020.

In January, the Buda Lions Club made the decision to hold its annual Wiener Dog Races at Buck’s Backyard this year. We look forward to supporting them and expect another great event.

Thank you again for your patience and feedback during the construction process.



Facebook Twitter Email

Other News in City News

Untitled design (8)

Red, White & Buda Fireworks Shows

Posted on: July 4, 2020
Hays County Offers Free COVID-19 Testing for Uninsured, Inderinsured and Indigent Resdidents (1)

Free COVID-19 Testing in Hays County

Posted on: June 25, 2020
Hays County Offers Free COVID-19 Testing for Uninsured, Inderinsured and Indigent Resdidents

Free COVID-19 Testing in Hays County

Posted on: June 11, 2020
Heat Advisory - June 9, 2020

Heat Advisory in Effect Until 7 PM

Posted on: June 9, 2020
Buda Parks and Recreation (3)

Buda Parks and Recreation Update

Posted on: June 8, 2020
Angry Cat

Pet Registration Information

Posted on: June 1, 2020
Reopening Texas (2)

Governor Abbott Expanded Openings

Posted on: May 26, 2020
City of Buda E-Billing

City of Buda E-Billing

Posted on: May 14, 2020
City Council Chamber 2019 - Smaller Version

City Council Meeting - April 7, 2020

Posted on: April 7, 2020
Good Friday Holiday - April 10, 2020

Good Friday Holiday - April 10, 2020

Posted on: April 6, 2020
Aquifer Storage Recovery

Aquifer Storage Recovery Pilot Well

Posted on: April 2, 2020
Buda Counts

Census Day - April 1, 2020

Posted on: April 1, 2020
Add a heading (6)

Hays County COVID-19 Dashboard

Posted on: March 31, 2020
Helen's Casa Alde Fire

Downtown Buda Fire

Posted on: March 15, 2020
Message From Mayor George Haehn

Message From Mayor George Haehn

Posted on: March 13, 2020
Buda Trash Off Pic 2020

Buda Trash-Off - Saturday, April 4

Posted on: March 4, 2020
Vote Image

March 3 Primary Voting Locations

Posted on: March 3, 2020
Transportation and Mobility Master Plan Twitter ENGLISH

Transportation and Mobility Master Plan

Posted on: February 21, 2020
water drops

Alliance Water Pipeline Project Update

Posted on: February 20, 2020
Dark Sky

International Dark Sky Community Survey

Posted on: January 31, 2020
Kenny Chat

Downtown Main Street Construction Update

Posted on: January 27, 2020
Heritage Tree - Artsy

City of Buda Amended Tree Ordinance

Posted on: January 23, 2020
Melissa McCollum

City of Buda Hires Director of Planning

Posted on: January 21, 2020
1327257_roadIsClosed_Standard_GDE (1)

Main Street Closure - Jan. 11 - Jan. 13

Posted on: January 6, 2020
happy new year

The Big Picture - Week of Dec. 30, 2019

Posted on: January 3, 2020
Buda Counts

Buda Counts: Census 2020

Posted on: December 31, 2019
New Years Holiday Schedule 2019

City of Buda New Years Holiday Schedule

Posted on: December 30, 2019
Buda-Logo-Final

2019 Year in Review

Posted on: December 23, 2019
fireworks Dec. 17

Fireworks Prohibited In and Around Buda

Posted on: December 23, 2019
Buda Trail of Lights 2

Trail of Lights at Stagecoach Park

Posted on: December 11, 2019
turkey 1

Buda Turkey Trot - Thursday, Nov. 28. 2019

Posted on: November 25, 2019
City Council Chambers UPDATED

Buda City Council Members Sworn In

Posted on: November 19, 2019
fm 967 open

FM 967 Is Now OPEN

Posted on: November 6, 2019
Buda Trail of Lights Picture

Trail of Lights at Stagecoach Park

Posted on: October 31, 2019
SCAM ALERT 2

Scam Alert - Oct. 23, 2019

Posted on: October 23, 2019
Downtown Buda Replica by Steve Ridenour

The Big Picture - Week of Oct. 14, 2019

Posted on: October 18, 2019
Bike Rodeo 11

The Big Picture - Week of Oct. 7, 2019

Posted on: October 11, 2019
Take Control of Your Health

Chronic Disease Self-Management Program

Posted on: September 24, 2019
boo da pumpkin

17th Annual Boo-Da Halloween

Posted on: September 11, 2019
Transportation and Mobility Master Plan Generic

Transportation & Mobility Master Plan

Posted on: September 6, 2019
1668733_onMyBallotB_Standard_GDE

New Hays County Voting Machines

Posted on: September 5, 2019
SCAM ALERT 2

SCAM ALERT

Posted on: September 3, 2019
labor day

Labor Day Holiday - Sept. 2, 2019

Posted on: August 27, 2019
Irrigation Pic 2

Maintaining Your Irrigation System

Posted on: August 21, 2019
Image of Indoor Volleyball Court

Sunfield Station Ribbon Cutting

Posted on: August 16, 2019
water smart 2

Water Smart Customer Portal

Posted on: August 16, 2019
road construction

REMINDER: Back to School Traffic Safety

Posted on: August 15, 2019
budafest 1

Budafest Canceled for 2019

Posted on: August 9, 2019
flame image

Hays County Burn Ban In Effect

Posted on: August 6, 2019
flame image

Prescribed Burn on Tuesday, July 30

Posted on: July 29, 2019
Main Street 2

Bond Project Updates - July 26, 2019

Posted on: July 26, 2019
modular home page portal and mobile

WaterSmart Customer Portal Open

Posted on: July 16, 2019
Buda Tower

The Big Picture Weekly Newsletter

Posted on: July 5, 2019
shareyourwisdom

May is Older Americans Month!

Posted on: May 9, 2017
National Drug Take-Back Day Pic

Buda PD/DEA Drug Take-Back Day

Posted on: April 10, 2017
Good Friday Holiday

Good Friday Holiday

Posted on: April 10, 2017
Easter Egg Hunt 11 - City of Buda

City of Buda Annual Easter Egg Hunt

Posted on: March 21, 2017
Municipal Site Live Camera Pic

Municipal Site Live Camera

Posted on: March 7, 2017
Austin Capitol Building

Buda Legislative Day at the Capitol

Posted on: March 2, 2017
Municipal Building Rendering

The Big Picture - Week of Feb. 20, 2017

Posted on: February 24, 2017
Big Picture Feb. 13.jpg

The Big Picture - Week of Feb. 13, 2017

Posted on: February 17, 2017
Presidents Day Holiday Pic

All City Offices Closed On President's Day

Posted on: February 13, 2017
Picture of Tommy Poer

The Big Picture - Week of Feb. 6, 2017

Posted on: February 10, 2017
Public Works Crew

The Big Picture - Week of Jan. 30, 2017

Posted on: February 3, 2017
Jan 23 Big Picture.jpg

The Big Picture - Week of Jan. 23, 2017

Posted on: January 27, 2017
Heritage Tree

Tree Relocation on Municipal Site

Posted on: January 26, 2017
Pic of Crew Working on Municipal Site

The Big Picture - Week of Jan. 16, 2017

Posted on: January 20, 2017
Buda City Seal

CITY PUTTING FLUORIDATION ON HOLD

Posted on: January 19, 2017
Picture of West Goforth Work

The Big Picture - Week of Jan. 9, 2017

Posted on: January 13, 2017
Christmas decorations taken down

The Big Picture - Week of Jan. 2, 2017

Posted on: January 6, 2017
Flyer of Focus Group on Aging

Focus Group on Aging

Posted on: January 4, 2017
Picture of Inside of Parks and Maintenance Building

The Big Picture - Week of Dec. 26, 2016

Posted on: December 30, 2016
Picture of Fireworks in the Sky

Fireworks Prohibited in City of Buda

Posted on: December 29, 2016
Animated Picture of a Christmas Tree

Christmas Tree Disposal Information

Posted on: December 27, 2016
Lee Urbanovksy Being Sworn-in

The Big Picture - Week of Dec. 19, 2016

Posted on: December 22, 2016
Flyer With Christmas Schedule Information

Christmas Holiday Schedule

Posted on: December 19, 2016
Crew Paving Interstate Drive

The Big Picture - Week of Dec. 12, 2016

Posted on: December 16, 2016
Picture of Stagecoach Park Pond Surrounded by Lighted Christmas Trees

The Big Picture - Week of Dec. 5, 2016

Posted on: December 9, 2016
The Big Picture Graphic

The Big Picture - Week of Nov. 28, 2016

Posted on: December 2, 2016
Event Cancelled Graphic

Budafest Cancelled

Posted on: December 2, 2016
Picture of Wiley Hopkins being sworn-in by City Secretary

The Big Picture - Week of Nov. 21, 2016

Posted on: November 23, 2016
Photo of Ray Creswell Sitting at Desk

City of Buda Hires First Project Manager

Posted on: November 23, 2016
the big picture week of nov. 14.JPG

The Big Picture - Week of Nov. 14, 2016

Posted on: November 18, 2016
Friends of the Buda Library Flyer

Friends of Buda Library Annual Book Sale

Posted on: November 14, 2016

The Big Picture - Week of Oct. 31, 2016

Posted on: November 4, 2016
Big Picture Graphic

The Big Picture - Week of Oct. 24, 2016

Posted on: October 28, 2016

Golf Cart Ordinance Reminder

Posted on: March 31, 2015

FAQs: Electro Purification Agreement

Posted on: February 9, 2015